Ask five different PMs how they determine whether a sprint is Green, Amber, or Red, and you’re likely to get five different answers. In most cases, determining RAG status relies on gut instinct masquerading as data – and that’s an issue. If a founder or product owner sees ‘Amber’ in the RAG column, they reasonably expect it to be based on some objective and specific criteria. Once it’s revealed to be subjective, the trust in the RAG status is lost the first time it doesn’t match reality.
This is a common scenario where a sprint has been reported as Green, but a founder discovers on Thursday that a critical bug was carried over or that a key feature was omitted. Once that happens, the next RAG ‘Green’ is met with skepticism and requests for the underlying data from the PM. A formulaic approach isn’t about bureaucracy; it’s the ability to stand behind the color of your status.
The solution is to define clear thresholds for your RAG as a formula before the sprint starts – and not during the report. Below is a practical RAG framework I use as a starting point for sprint reporting. It evaluates three dimensions: schedule variance, quality, and delivery against commitment. The thresholds are configurable, so teams should agree on them before the sprint begins and adjust them to suit their delivery environment.
Why Gut Feeling RAG Status Fails
Before diving into the formula, it’s useful to highlight the issues without one:
- Different PMs on the same program may report the same situation differently, breaking report consistency
- Stakeholders lose trust in the RAG status once a ‘Green’ sprint turns out to have no warning for stakeholders
- Without clear thresholds, the RAG status is a reactive indicator instead of predictive
- Teams feel pressured or incentivized to manipulate the color of the RAG based on their conversations with the founder
A formulaic approach to your RAG solves all four, because the color reported is derived from data, not how the conversation with the founder went that week.
The 3 Inputs That Should Drive Your RAG Status
1. Progress Variance

Compare the actual schedule of your sprint/milestone to the planned schedule.
Formula: Progress Variance (%) = Actual % Complete − Planned % Complete
Compare the actual percentage of planned work completed with the percentage that should have been completed by the reporting date. This simple progress measure is intended for sprint and milestone reporting; it is not the earned-value Schedule Variance (SV) formula.
🟢 Green: Variance ≥ -5 percentage points
🟡 Amber: Variance ≥ -15 and less than -5 percentage points
🔴 Red: Variance less than -15 percentage points
2. Open Bug Ratio
Compare the number of unresolved bugs identified during the reporting period with the total number of bugs identified during that same period. Define the reporting period and bug-counting rules consistently. Track open critical and blocker bugs separately because their severity may justify an escalation regardless of the overall ratio.
Formula: Open Bug Ratio = Open Bugs ÷ Total Bugs Identified
If no bugs were identified during the reporting period, the ratio is not applicable rather than zero. Report it as N/A and investigate whether the testing and reporting data are sufficient to assess quality.
🟢 Green: No open critical/blocker bugs, and open bug ratio ≤ 10%
🟡 Amber: No open critical/blocker bugs, and open bug ratio greater than 10% but ≤ 25%
🔴 Red: Any open critical/blocker bug, or open bug ratio greater than 25%
Edge case: If no bugs were identified, the open bug ratio is undefined because the denominator is zero. Report it as N/A rather than 0%, and assess quality using the available test results and coverage information. Always flag open critical or blocker bugs separately.
3. Velocity Attainment

Compare the story points associated with work completed and accepted during the sprint against the story points committed at the agreed baseline.
Formula: Commitment Completion Ratio = Completed Story Points ÷ Committed Story Points × 100
🟢 Green: ≥ 90%
🟡 Amber: ≥ 70% and less than 90%
🔴 Red: Less than 70%
This ratio is a planning and delivery indicator, not a measure of individual productivity. Story points are team-specific estimates and should not be compared across teams or used to encourage inflated estimates. If no story points were committed, report the ratio as N/A.
How to Combine the Three Inputs Into One Overall Status
Once schedule, quality, and commitment completion have individual RAG statuses, you need a consistent rule for determining the overall result. One conservative approach is the cascade rule: the overall status takes the worst colour among the three inputs. This prevents a strong result in one area from hiding a significant problem in another. Teams may choose different aggregation rules, but they should define and communicate the rule before reporting begins.
- If schedule is Green, quality is Green, but velocity is Red, your overall status is Red.
- This prevents a strong schedule number from masking a genuine quality or delivery-capacity problem.
A quick worked example: If in a sprint Actual Complete is 78% against a Planned 85% (a -7% variance – Amber), with no open critical bugs and a 12% open bug ratio (Amber), and a Velocity of 94% of committed story points (Green) – the cascade rule applies the worst single input (Schedule and Quality), and your overall sprint is Amber. That’s the value of calculating each of the three inputs separately: a strong result in one dimension does not cancel out warning signs in the others.
It’s exactly this approach that is applied to the RAG Status slide of my Weekly Project Status Report Template, where scope, schedule, budget, and quality are tracked as different colored inputs.
What to Include Alongside the RAG Status
A colour alone does not explain the situation or tell stakeholders what happens next. For every Amber or Red result, include:
- Reason: What specific condition triggered the status?
- Impact: What could happen to the sprint or milestone if the issue remains unresolved?
- Owner: Who is responsible for addressing or monitoring it?
- Next action: What corrective or mitigating action is planned?
- Target date: When should stakeholders expect an update or resolution?
A Green status should also be supported by evidence. The purpose of RAG reporting is not simply to display a colour, but to help stakeholders understand delivery health and make timely decisions.
Quick Self-Check 🎯
Using the quick calculation above, run your current sprint through the formula:
- Calculate your schedule variance using actual vs. planned % complete
- Calculate your open bug ratio, and check for any open critical bugs
- Calculate velocity % against committed story points
- Combine the three with the cascade rule – your overall status is the worst of the three
- Record the reason, owner, and next action for every Amber or Red indicator.
If all three indicators are Green, the available data suggests that the sprint is progressing within the agreed thresholds. Continue monitoring rather than treating Green as a guarantee of successful completion.
Get the Template
If you use this framework regularly, a structured reporting template can save time and make the calculations more consistent. The Weekly Project Status Report Template provides a reporting structure for communicating project health, while the PM Toolkit for Web & App Teams offers additional project-management resources. Choose the one that best fits your reporting needs.
Related read: 9 Powerful Slides Your Weekly Status Report Template Needs to Impress Founders
Related read: 7 Sprint Planning Templates That Save Web & App Teams From Chaos
Frequently Asked Questions (FAQ)
Are RAG thresholds consistent across different teams?
No. The percentages above are a good starter baseline, but teams with highly volatile scope (new products, R&D-heavy work) may want broader Amber bands than mature, stable teams.
What’s a situation where schedule and velocity disagree?
Schedule and commitment completion can disagree when the team is progressing against its planned dates but completing less committed work than expected, or when the team has completed its committed work while a milestone is falling behind. Under the cascade rule described in this tutorial, the overall status takes the worst of the individual indicators. The disagreement should prompt an investigation into scope changes, dependencies, estimation, and the way progress is being measured.
How does TPM-level RAG differ from a single team PM’s RAG?
At program level, a Technical Program Manager may consolidate RAG indicators from several teams. If the same cascade rule is used, the program status takes the worst reported team status. However, the program report should also explain the impact, dependencies, and corrective actions rather than simply displaying the worst colour. Organizations may define different escalation and aggregation rules, provided they are explicit and consistently applied.
What about scope and budget; shouldn’t those be factored into the RAG?
They absolutely should, and many teams use the same RAG framework against a fourth and fifth inputs (a scope-change count threshold, and a budget-burn-rate percentage, respectively) – this tutorial focuses on schedule, quality, and velocity because it’s the three inputs available from the sprint data, without needing finance or scope-change tracking systems, but the same cascade rule applies cleanly if you add more dimensions.
Your Turn 💬
Does your current status reporting make use of defined thresholds like this, or is RAG status still more of a subjective call on your team? Throw a comment below, and I’ll read every one.
